Transcript
00:02This video details how to terminate. Hubble's plugs with co Burlock termination.
00:07All co burlock termination plugs come with a jack body and a wire manager.
00:11The only tools needed to complete the termination are a cable jacket,
00:15stripper and flush wire cutters.
00:17Let's get started.
00:18The first step is to feed the cable through the wire, not then strip the cable jacket by
00:23scoring the outer inch of the jacket about 1 to 2 inches from the end,
00:27making sure not to damage the conductors. Once the outer jacket is removed,
00:32fan wires out and remove any non conductive elements such as centers,
00:35splines, rip cord and the next shielding.
00:40Now that the inner wires are exposed, rotate the wire manager to match the label colors to
00:45the wire colors.
00:56Minimize crossing of pairs, only one pair should need to cross another
01:07bend the wire pairs over and untwist slightly so they can be pulled into their designated
01:11grooves, lock wires into place by pulling down on the free ends and the cable jacket.
01:22During this step, make sure the center spacer is at the bottom of the wire manager away from
01:27the termination plane.
01:28This helps with lacing by providing room for your thumb and ensures nothing will impede the
01:33wire manager from mating with the plug contacts.
01:41Next, use flush cutters to cut the wires flush to the sides of the wire manager.
01:56Then open the cover lock and orient the wire manager to the plug body.
02:04Close the cover lock until the locking tabs snap into place.
02:08Securing the termination physically, confirm the cover lock is engaged by trying to separate
02:13the back halves. Lastly, tighten the wire nut to provide
02:16additional strain relief.
02:18If needed, you can easily re terminate up to 25 times when finished.
02:22Perform all required testing to MP TL limits submit results to Hubble if you are applying
02:28for our 25 year mission critical application assurance warranty.